US Army Corps of Engineers
San Francisco District

Contact

General Questions
415-503-6708
450 Golden Gate
San Francisco, CA 94102

Napa River Salt Marsh Restoration

NAPA RIVER, SALT MARSH RESTORATION
CONSTRUCTION

PROJECT LOCATION AND DESCRIPTION

The Napa-Sonoma Marsh Wildlife Area is located along the northern portion of the San Pablo Bay, approximately 45 miles north of San Francisco, California. The marsh originally comprised 25,000 acres, but agriculture and development have reduced it by 64%. In 1994, the Cargill Salt Company ceased production and sold over 9,800 acres of land in the project area to the State of California, managed by the California Department of Fish and Wildlife (DFW). The Napa Salt Marsh Restoration Project restores approximately 4,500 acres of the 9,800 acres Napa-Sonoma Marsh Wildlife Area. The restoration of Ponds 6, 6A, 7, 7A and 8 requires removing “bittern” (a byproduct of salt production) from Pond 7 and improving water circulation and the ability to manage water levels within the ponds to benefit shorebirds and waterfowl.
 

TOTAL FUNDING

 

TOTAL COST

$ 41,197,272

FEDERAL COST

$ 26,676,512

NON-FEDERAL COST

$ 14,520,760

 

 

TOTAL FEDERAL COST THROUGH FY 2017

26,676,512

FY 2020 BUDGET

$                  0

COST TO COMPLETE

$             TBD

 

FY 18 ACCOMPLISHMENTS

  • Continue construction of Ponds, 6, 6A, 7, 7A, and 8
  • Continue project monitoring

FY 19 ACCOMPLISHMENTS

  • Developed DRAFT O&M Manual for Review by NFS
  • Reconciled cost share records, and requested $3,047,816 and $339,050 in cash for the restoration and recreation cost shares  

ISSUES AND OTHER INFORMATION

  • The NFS has been advised they are out of cost share balance since June 2018 and they have developed a tentative payment plan to balance the cost shares. April 2019 for Recreation and July 2019 for restoration.
  • The Non-Federal Sponsor (NFS) for Feasibility and Design was the California Coastal Conservancy. The NFS for Construction is the CDFW. The California Coastal Conservancy will continue to be involved as a project partner.
  • The final Feasibility Report, completed in June 2004, recommended that seven of the twelve salt ponds—4, 5, 6, 6A, 7, 7A and 8—be restored to tidal and managed wetlands. The Chief’s report was signed in December 2004. Office of Management and Budget (OMB) clearance was provided in December 2005.
  • Design and construction of Ponds 1, 1A, 2, 2A, 3, 4, and 5 are complete.
  • The NSF constructed Ponds 4 and 5 and completed 90% design drawings, specifications, and estimates for Ponds 6-8.
  • The Water Resource Development Act (WRDA) 2007 authorized crediting the NFS for work completed on the approved project before a PPA is signed, as identified above.
  • The Corps determined in-kind credit through an Integral Determination Report (IDR) that was approved in July 2010.
  • The total project authorization in WRDA 2007 is $134,500,000 with an estimated Federal cost of $87,500,000 and an estimated non-Federal cost of $47,000,000. Also included in the authorization are non-policy compliant components to restore or enhance Salt Ponds 1, 1A, 2 and 3, and construction of a recycled-water pipeline extending from the Sonoma Valley County Sanitation District Pumping Plant and the Napa Sanitation District Waste Water Treatment Plant.

CONGRESSIONAL INTEREST

  • 5th District, Rep. Mike Thompson

POINT OF CONTACT

  • Deputy for Project Management, Edwin S. Townsley, (415) 503-6593.

Updated on 27 February 2019

 

Click Map to Zoom In