Project location and description

This is a flood-control project on Corte Madera Creek in Marin County, California.  Corte Madera Creek  and its tributaries drain an area of 28 square miles, and discharge into the west side of San Francisco Bay nine miles north of the Golden Gate Bridge. This flood-control project has been built in four separate units. Units 1, 2, and 3 are on Corte Madera Creek extending from San Francisco Bay through the towns of Corte Madera, Larkspur, Kentfield, and Ross. The Unit 4 study area includes Corte Madera Creek upstream from the Unit 3 concrete channel, located about 600 feet downstream of the Lagunitas Road Bridge, to the Sir Francis Drake Boulevard Bridge and the lands adjacent to the creek.

Total funding

 

 

 

TOTAL COST

                     $   37,100,000

FEDERAL COST

                     $   21,900,000

NON-FEDERAL COST

                     $   15,200,000

 

 

TOTAL FEDERAL COST THROUGH FY 2013

                     $   16,380,000

ARRA FUNDING

                     $                 0

FY 2014 BUDGET

                     $                 0

COST TO COMPLETE

                     $     5,520,000

FY 13 accomplishments

  • Establish the NED Plan.
  • Continue development on the GRR and NEPA documents.

FY 14 accomplishments (based on the availability of funds)

  • Finalize the alternatives matrix.
  • Hold Alternative Formulation Briefing (AFB).
  • Complete EIS/R.

Issues and other information

  • The Marin County Flood Control and Water Conservation District is the Non-Federal Sponsor (NFS).
  • This project did not receive funds from the American Recovery and Reinvestment Act of 2009 (ARRA), Title IV, Pub. L. No. 111-5, 123 Stat. 115, Feb. 17, 2009.
  • During development of the GRR, an agreement was reached to develop a concept plan based on the 1996 Marin County Board of Supervisors’ Design Guidelines for a consensus plan. The 1999 Project Study Plan initiated the GRR and supplemental environmental reports and reviews.
  • In 2001, Congressional Representatives, citizens, and elected officials of the towns of Ross, Kentfield, Corte Madera and Larkspur participated in the Design Advisory Committee meetings, public meetings, and town screenings to help Marin County identify a Locally Preferred Plan (LPP) at less than the 100-year flow.
  • USACE studies in FY 02 showed that the project would not significantly affect the already poor survivability of historically significant Lagunitas Road Bridge, and the Town of Ross begun replacement of the bridge in 2010.
  • In 2003, Ross and Marin County changed the LPP and endorsed design flows that would pass through the town in the creek channel. This endorsement marked the effective start of the GRR Phase 2. Fish biologists, funded by a grant to the Friends of Corte Madera Creek, used USACE’s FY 05 Geotechnical borings to propose designs for the Unit 4 channel. The 1966-authorized cost-sharing and financing requirements apply as long as the project remains as authorized (for flood control up to project limits at the Sir Francis Drake Bridge in Ross).
  • In the summer of 2010, the Ross Valley Watershed Technical Group (headed by the Marin County Flood Control and Water Conservation District) was created to address flood risk management through a watershed-wide approach. As a result of the proposed mitigation measures throughout the watershed, the expected capacity at Unit #4 for the 100-yr event is 6,000 cfs. The USACE has included an alternative that looks at a 6,000 cfs capacity at Unit #4.

Congressional interest

  • 2nd District, Rep. Jared Huffman

Point of contact

  • Deputy for Project Management, Arijs A. Rakstins, (415) 503-6720