CONTINUING AUTHORITY PROGRAM, SECTION 204
PROJECT LOCATION AND DESCRIPTION
The proposed project would address the loss of sand and beach fronting critically eroding areas along Beach Boulevard in the central portion of the City of Pacifica. The area experiences erosion rates of more than 2.5 feet annually, that threaten roads, critical wastewater and stormwater facilities, a beach promenade, the Pacifica Municipal Pier. Directly adjacent to the study area is Laguna Salada, a large brackish lagoon, host to endangered California red-legged frogs and San Francisco garter snakes. Potential sand provided from the 204 Program would complement other measures under consideration to abate erosion in the area.
TOTAL FUNDING
TOTAL COST $ 1,040,000
FEDERAL COST $ 1,040,000
NON-FEDERAL COST $ NA
TOTAL FEDERAL COST THROUGH FY 2023 $ 50,000
FY 2024 BUDGET $ 300,000
COST TO COMPLETE $ 690,000
FY23 ACCOMPLISHMENTS
- Scoping for Federal Interest Determination
FY24 ACCOMPLISHMENTS
- Draft Federal Interest Determination Fact Sheet
ISSUES AND OTHER INFORMATION
- Beach Boulevard is one of two CAP studies along the Pacifica Coastline. The other study is Esplanade Avenue CAP 103. USACE completed the Federal Interest Determination for Esplanade and is now preparing a Project Management Plan to inform execution of the Feasibility Cost Sharing Agreement.
CONGRESSIONAL INTEREST
- 16th District, Rep. Anna Eshoo
POINT OF CONTACT
- Deputy for Project Management, Thomas R. Williams, 415-503-6560