Dry Creek (Warm Springs Dam) Restoration

DRY CREEK (WARM SPRINGS DAM) RESTORATION CONSTRUCTION

PROJECT LOCATION AND DESCRIPTION

The project is located along Dry Creek, below USACE Warm Springs Dam (WSD) and near the City of Healdsburg in Sonoma County, CA. The project will restore approximately 47 acres of stream, floodplain and riparian habitat along 2.6 miles of stream. Restoration measures include increasing habitat complexity and improving hydrologic connectivity with the floodplain by constructing combinations of riffles, large wood structures, backwaters, side channels, and alcoves pool features. Riparian habitat will be improved through invasive species reduction and riparian revegetation with native species.  

 

TOTAL FUNDING1

 

TOTAL COST

                       $  49,106,000

FEDERAL COST

                       $  31,752,000

NON-FEDERAL COST

                       $  17,354,000

 

 

TOTAL FEDERAL COST THROUGH FY 2023

                         $  31,752,000

FY 2024 BUDGET

                         $  0

COST TO COMPLETE

  1 Includes Feasibility (50/50) and PED (75/25) funding.

    $ 0

           

 

 

FY23 ACCOMPLISHMENTS

  • PHASE I: Completed construction of the majority of subarea Reach 10. There is a small portion of the project remaining; construction is scheduled to be complete in the FY24 construction season.
  • PHASE II: Awarded construction contract and completed the majority of subarea 4C. Construction of Phase II is scheduled to be complete in the FY24 construction season.

FY24 ACCOMPLISHMENTS

  • Construction is suspended during the northern California rainy season (generally October – May). Phase I and Phase II construction will re-commence in JUNE 2024

ISSUES AND OTHER INFORMATION

  • Sonoma Water (formerly Sonoma County Water Agency) is the Non-Federal Sponsor (NFS).
  • A Biological Opinion (BO), issued by the National Marine Fisheries Service, mandates that SCWA and USACE perform various Reasonable and Prudent Measures to save threatened and endangered salmonid species. Implementation of this ecosystem restoration project will help comply with these BO requirements.
  • Real estate negotiations between landowners and the non-Federal Sponsors are projected to delay the Phase III portion of Dry Creek by approximately two years

CONGRESSIONAL INTEREST

  • 2nd District, Rep. Jared Huffman
  • 5th District, Rep. Mike Thompson

POINT OF CONTACT

  • Deputy for Project Management, Thomas R. Williams, 415-503-6560

Updated on 29 February 2024

           

Click Map to Zoom In

Contact

Projects & Planning General Info
415-503-3674
450 Golden Gate
San Francisco, CA 94102