TOTAL FUNDING:
|
|
|
|
TOTAL COST:
|
$ 117,200
|
FEDERAL COST:
|
$ 117,200
|
NON-FEDERAL COST:
|
$ 0
|
|
|
TOTAL FEDERAL COST THROUGH FY 2006:
|
$ 117,200
|
FY 2007 BUDGET:
|
$ 0
|
COST TO COMPLETE:
|
$ 0
|
FY 07 accomplishments: No work is anticipated for FY07 since the study was not funded. Those studies that are named in appropriations reports are given higher priority for funding.
FY 08 accomplishments: If FY08 funds were provided and a local sponsor could be identified, an Initial Assessment could be prepared and a Planning Design Analysis Report could be initiated.
ISSUES AND OTHER INFORMATION: Study initiation is suspended indefinitely due to lack of funding.
CONGRESSIONAL INTEREST: 1st District, Rep. Mike Thompson.
POINT OF CONTACT: Deputy District Engineer for Civil Works, Arijs Rakstins, (415) 503-6720