TOTAL FUNDING:
|
|
|
|
TOTAL COST:
|
$3,000,000
|
FEDERAL COST:
|
$3,000,000
|
NON-FEDERAL COST:
|
$0
|
|
|
TOTAL FEDERAL COST THROUGH FY 2006:
|
$00
|
FY 2007 BUDGET:
|
$0 1/
|
COST TO COMPLETE:
|
$3,000,000
|
FY 06 ACCOMPLISHMENTS: No work is anticipated for FY06 since the study was not funded. Those studies that are named in appropriations reports are given higher priority for funding.
FY 07 ACCOMPLISHMENTS: If funds were provided, an Initial Assessment could be completed and a Feasibility Study and Detailed Project Report could be initiated.
ISSUES AND OTHER INFORMATION: Study initiation is suspended indefinitely due to lack of funding. The Moss Landing Harbor District General Manager requested Corps assistance with an erosion problem that appears to be caused by the jetties. The way the jetties were built appears to cause an “eddy” effect to the south of the entrance channel, creating erosion on the immediately adjacent property and an extremely high volume of sediment deposition on the next adjacent property.
CONGRESSIONAL INTEREST: 17th District, Rep. Sam Farr
POINT OF CONTACT: San Francisco District, (415) 503-6720
For questions, suggestions, or comments: cespn-pm@usace.army.mil