Napa Valley Watershed Management (I)

NAPA VALLEY WATERSHED MANAGEMENT
INVESTIGATIONS 

PROJECT LOCATION AND DESCRIPTION

The Napa Valley Watershed is located within the northern portion of the San Pablo Bay drainage basin in Napa County, California. The purpose of this study is to complete a watershed analysis to address problems and opportunities through water and related land-resource management.

 

TOTAL FUNDING

 

TOTAL COST

                     $     5,598,000

FEDERAL COST

                     $     2,848,000

NON-FEDERAL COST

                     $     2,750,000

 

 

TOTAL FEDERAL COST THROUGH FY 2018

                     $     1,065,000

FY 2019 BUDGET

                     $                 0

COST TO COMPLETE

                     $                0

FY 18 ACCOMPLISHMENTS

  • Evaluate Work In Kind Contributions from the Non Federal Sponsor
  • Balance the cost share and complete Fiscal Closeout

FY 19 ACCOMPLISHMENTS 

  • None

ISSUES AND OTHER INFORMATION

  • The Napa County Flood Control and Water Conservation District is the Non-Federal Sponsor (NFS).
  • This project did not receive funds from the American Recovery and Reinvestment Act of 2009 (ARRA), Title IV, Pub. L. No. 111-5, 123 Stat. 115, Feb. 17, 2009.
  • The Napa County Board of Supervisors appointed a Napa Valley Watershed Conservancy Board and Technical Review Panel to assist in the study development. These locally-organized and lead entities are critical to the on-going development of study tasks and the completion of the watershed management plan. The NFS is concentrating local resources to implement a large flood-reduction project with the Sacramento District, USACE.  If watershed funds could be obtained without having a negative impact on the Napa River flood reduction project, the NFS would pursue funding.
  • Due to projected costs in completing the watershed study a collaborative agreement was made with the sponsor to terminate the project. They have submitted their work in kind estimates which will be the basis for calculating the cost share balance and closing out the study.

CONGRESSIONAL INTEREST

  • 5th District, Rep. Mike Thompson

POINT OF CONTACT

  • Deputy for Project Management, Arijs A. Rakstins, (415) 503-6720

Updated on 26 February 2018

Click Map to Zoom In