San Francisco Harbor Ocean Beach

 

 

 

 

 

 

 

 

 

The project is located along San Francisco Ocean Beach.  Severe and persistent erosion threatens municipal wastewater infrastructure.  Dredged material from the maintenance of the San Francisco main ship channel, the gateway to San Francisco Bay, was utilized to construct protective sand dunes along the eroded stretch of beach to provide shoreline protection and environmental and recreational benefits.

 

TOTAL FUNDING

 

TOTAL COST

                        $ 13,370,000

FEDERAL COST

                        $ 10,850,000

NON-FEDERAL COST

                        $   2,520,000

 

 

TOTAL FEDERAL COST THROUGH FY 2022

                         $   6,265,000

FY 2023 BUDGET

                         $   0            

COST TO COMPLETE

                         $   4,585,000

 

FY 22 accomplishments

  • Completed Design Phase
  • Signed Construction PPA
  • Executed Implementation (construction of dunes)
  • Team acquired all necessary environmental permitting to construct in August 2021

FY 23 ACCOMPLISHMENTS

  • Closeout of project.

ISSUES AND OTHER INFORMATION

  • The City and County of San Francisco are the Non-Federal Sponsor (NFS).
  • This project did not receive funds from the American Recovery and Reinvestment Act of 2009 (ARRA), Title IV, Pub. L. No. 111-5, 123 Stat. 115, Feb. 17, 2009.
  • New Section 204 implementation guidance has not been fully interpreted and rendered by HQ.  However, the approved DPR was reviewed at HQ in 2016 and the project was allowed to go forward with signing a PPA.
  • The NFS and Corps have agreed to the bifurcation of the PPA into a design PPA (DA) and construction PPA to alleviate the NFS’s CEQA issue. 
  • The NFS completed CEQA before the signing of the construction PPA.
  • Approximately, 440,000 cubic yards of material was dredged from the San Francisco Main Ship Channel and placed on the beach to construct the dune.
  • The NFS has expressed interest in coordinating with the Corps about future placements on the beach to support the dune.
  • Recent discussions with NFS have occurred about the best pathways for obtaining the most streamlined strategies (i.e., Section 125A) for carrying out future placements on a frequent basis.

CONGRESSIONAL INTEREST

  • 11th District, Rep. Nancy Pelosi

POINT OF CONTACT

  • Deputy for Project Management, (415) 503-6593.

Updated on 14 February 2023

Contact

Projects & Planning General Info
415-503-3674
450 Golden Gate
San Francisco, CA 94102