P.L. 84-99 Repairs Done

Site 1 RepairedSite 2 RepairedSite 3 Repaired

For more information or questions

If you have any questions or seek more information about any projects concerning the Pajaro River, just click here to send an email: Pajaro-River@usace.army.mil, and we'll get back to you. 

Pajaro River LB and RB P.L. 84-99 Flood Risk Management and Coastal Emergencies (FCCE)

PROJECT LOCATION AND DESCRIPTION

The Pajaro River Federal Levee Project, authorized by Section 10 of the Flood Control Act of 1944, Pub L. No. 534, 58 Stat. 900, primarily consists of earthen levees, with a low flow channel, at the downstream end of the Pajaro River watershed located in Santa Cruz, Monterey, and San Benito counties of California. The levees were constructed in 1949 and designed to contain a 19,000 cfs design discharge, which is an estimated 10% (1/10) annual exceedance probability.

The Pajaro River Levees have had multiple non-federal sponsors (NFS) responsible for different sections of the levees since the construction of the levee system. The Pajaro Regional Flood Management Agency (PRFMA), a joint powers authority of the County of Santa Cruz, Santa Cruz County Flood Control and Water Conservation Zone No. 7, the County of Monterey, the Monterey County Water Resources Agency, and the City of Watsonville, was formed in 2021.  PRFMA took on sponsorship of the Pajaro Levees on 1 July 2023 to plan, finance and implement projects and programs to reduce flood risk from the lower Pajaro River and its tributaries in Santa Cruz and Monterey Counties. 

Northern California received a series of atmospheric rivers (ARs) in January and March 2023. The Pajaro Levee – Left Bank (Pajaro LB) breached on the evening of Friday,10 March 2023. The initial breach (Site 1) was approximately at River Mile (RM) 10, flooding the town of Pajaro. The overflow from the breach resulted in partial breach damage at the Highway 1 crossing (Site 2) and a third breach downstream, located approximately at RM 1 (Site 3).  The Pajaro Levee – Right Bank (Pajaro RB) experienced severe erosion in multiple locations from January through March.

 

TOTAL FUNDING

 

TOTAL PROJECT COST ESTIMATE

$18.2 million

Left Bank Repairs (estimated)

$15.5 million

Right Bank Repairs (estimated)

$ 2.7 million

 

 

FEDERAL COST

$ 18.2 million

TOTAL FUNDED TO DATE

$15.7 million

 

 

FY23 ACCOMPLISHMENTS

  • Site 1 Repair Contract Awarded July 2023, Construction Completed Nov 2023
  • Site 3 Repair Contract Awarded August 2023
  • Site 2 Repair Contract Awarded Dec 2023

FY24 ACCOMPLISHMENTS

  • Site 3 Levee Construction Completed Jan 2024
  • Site 2 Levee Construction Competed Feb 2024
  • Pajaro RB E&D 65% Completed Feb 2024

ISSUES AND OTHER INFORMATION

  • Pajaro LB Site 3 – NFS requested culvert replacement in addition to levee repair.  Culvert repair is 100% funded by NFS to be contracted by Corps contractor.  Funds received from NFS, work is pending weather.
  • Pajaro RB – 14 erosion sites to be repaired, construction to be completed by Dec 31, 2024

CONGRESSIONAL INTEREST

  • 19th District, Rep. James Panetta

POINT OF CONTACT

  • Deputy for Project Management, Thomas R. Williams, 415-503-6560

Updated on 29 February 2024

Contact

Projects & Planning General Info
415-503-3674
450 Golden Gate
San Francisco, CA 94102