TOTAL FEDERAL COST THROUGH FY 2009:
|
|
ARRA FUNDS
|
|
|
|
|
|
AMOUNT THAT COULD BE USED IN FY 2010
|
|
FY 09 AND FY 10 ACCOMPLISHMENTS: Unobligated funds from prior years will be used for closeout of the breakwater repair contract awarded late September 2008.
ISSUES AND OTHER INFORMATION: Project name change, formerly Half Moon Bay, was authorized by Water Resources Development Act 1990. The west end of the west breakwater was repaired in FY96.
CONGRESSIONAL INTEREST: 12th District, Rep. Jackie Speier; 14th District, Rep. Anna Eshoo.
POINT OF CONTACT: Deputy District Commander for Civil Works, Arijs Rakstins (415) 503-6720