2022 Dredging

Dredge with open clamshell on the water with hills in the background

San Rafael Creek

SAN RAFAEL CREEK
OPERATIONS AND MAINTENANCE

 

PROJECT LOCATION AND Description

Located along the San Francisco Bay in Marin County, San Rafael Creek Channel is a shallow draft channel used mainly for light commercial and recreational activities. The O&M schedule provides for a seven-year cycle for maintenance dredging to a depth of -8 feet Mean Lower Low Water (MLLW) for the Across-the-Flats Channel in San Francisco Bay to the mouth of San Rafael Creek, and a four-year cycle for maintenance dredging to a depth of -6 feet MLLW for the Inner Canal Channel to the head of navigation at the Grand Street Bridge in the City of San Rafael. The Inner Canal and Across-the-Flats Channels were last dredged in FY 12 to a depth of -5 feet MLLW, with placement of the dredged material at the San Pablo Bay Disposal Site (SF-10), an unconfined aquatic disposal site.

TOTAL FUNDING

 

 

 

TOTAL COST

N/A

FEDERAL COST

N/A

NON-FEDERAL COST

N/A

 

 

TOTAL FEDERAL COST THROUGH FY 2025

$0

FY 2026 BUDGET

$7,370,000

COST TO COMPLETE

N/A

 

FY 25 ACCOMPLISHMENTS

  • Updates are in progress. Check back soon for more information.

FY 25 ACCOMPLISHMENTS

  • Planning and design for FY26 dredging of the Inner Canal is scheduled to start in summer 2025.
  • Updated hydro surveys will be conducted and posted on our website. The latest surveys are from August 2024.

FY 24 ACCOMPLISHMENTS

  • Approximately 11,700-CY was placed for beneficial re-use from the Suisun Bay Channel O&M Maintenance Dredging which completed 30 Nov 23. The remaining 49,600-CY of beneficial re-use debt will carry-over into FY25. 
  • The San Rafael Creek Channel, 2023 Chemistry Verification, Sampling Area 7 Report was provided to Dredged Material Management Office (DMMO) in February 2024 and will be provided to NMFS. 

ISSUES AND OTHER INFORMATION

  • The City of San Rafael is the NFS.

CONGRESSIONAL INTEREST

  • 2nd District, Rep. Jared Huffman

POINT OF CONTACT

  • Deputy for Project Management, Thomas R. Williams, 415-503-6560

Updated on 20 February 2026

Click Map to Zoom In

Contact

Projects & Planning General Info
415-503-3674
450 Golden Gate
San Francisco, CA 94102