SAN RAMON VALLEY RECYCLED WATER PROJECT
CONSTRUCTION
PROJECT LOCATION AND DESCRIPTION
This project is located in the San Ramon Valley approximately 25 miles east of San Francisco. It includes parts of Contra Costa and Alameda counties. The project area runs from Danville south to Dublin. The project will facilitate the use of recycled water to replace potable water for landscape irrigation. The Corps’ portion of this project includes the construction of one pump station and 8-14 miles of pipeline.
TOTAL FUNDING
|
|
TOTAL COST
|
$ 14,752,000
|
FEDERAL COST
|
$ 11,064,000
|
NON-FEDERAL COST
|
$ 3,688,000
|
|
|
TOTAL FEDERAL COST THROUGH FY 2018
|
$ 11,064,000
|
FY 2019 BUDGET
|
$ 0
|
COST TO COMPLETE
|
$ 0
|
FY20 and FY21 ACCOMPLISHMENTS
- Perform financial close out.
ISSUES AND OTHER INFORMATION
- The Dublin-San Ramon Services District/East Bay Municipal Utility District Recycled Water Authority is the Non-Federal Sponsor (NFS).
- Three contracts have been completed for one pump station and over 10,000 feet of pipe in San Ramon and Danville.
CONGRESSIONAL INTEREST
- 11th District, Rep. Mark DeSaulnier
- 15th District, Rep. Eric Swalwell
POINT OF CONTACT
- Deputy for Project Management, (415) 503-6593.