Under the Corps' Regulatory Program, a public notice is the primary method for advising all interested parties of a proposed activity for which a permit is sought. Public notices are also published to inform the public about new or proposed regulations, policies, guidance or permit procedures.

We are requesting public comments on many Public Notices (PNs) concurrently; please pay careful attention to the file number and the comments Due Date.

Email comments are preferred.  To submit comments in writing, send them to the attention of the Project Manager listed in the Public Notice title block.  All comments should reference the PN file number and be submitted by the Response Required Date on the PN.


The Public Notices are in pdf format. To read the files you may need to download and install Adobe Acrobat Reader or another comparable program

 Receive Regulatory Program Public Notices

If you would like to be added to one or more of the public notice mailing lists, send an email to cespn-rg-info@usace.army.mil with your contact information (Name, Organization, Mailing Address, Email, Phone Number) and the notification list(s) you would like to be added to:

All Counties within San Francisco District 
- or -
Alameda  |  Contra Costa  |  Del Norte  |  Humboldt  |  Marin  |  Mendocino
Monterey  |  Napa  |  San Benito  |  San Francisco  |  San Luis Obispo  |  San Mateo
Santa Clara  |  Santa Cruz  |  Siskiyou  |  Solano  |  Sonoma  |  Trinity

 


If you are on our mailing list and your contact information changes, please notify cespn-rg-info@usace.army.mil with your new addresses.  E-mails returned due to a non-functioning address will be removed from notification lists.

SPN-2018-00138N - Lower Mattole River Restoration Project

Published June 5, 2018
Expiration date: 7/7/2018

Lower Mattole River Restoration Project


PUBLIC NOTICE NUMBER: SPN-2018-00138N
PUBLIC NOTICE DATE: June 6, 2018
COMMENTS DUE DATE: July 6, 2018
PERMIT MANAGER: L. Kasey Sirkin | TELEPHONE: 707-443-0855 | E-MAIL: l.k.sirkin@usace.army.mil


1. INTRODUCTION:


United States Bureau of Land Management (POC: Ms. Molly Brown, 707-825-2300), 1695 Heindon Road, Arcata, California 95521, has applied to the U.S. Army Corps of Engineers (USACE), San Francisco District, for a Department of the Army Permit to discharge fill material into jurisdictional waters of the United States associated with the restoration of aquatic habitat in the Lower Mattole River. This Department of the Army permit application is being processed pursuant to the provisions of Section 404 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1344 et seq.) and Section 10 of the Rivers and Harbors Act of 1899, as amended (33 U.S.C. § 403 et seq.).


2. PROPOSED PROJECT:


Project Site Location: Mattole River estuary and approximately 3 miles upstream, Humboldt County, California, at center point latitude 40.291265°N and longitude -124.3695°W. See attachment 1.


Project Site Description: The Mattole River is a perennial river that drains an area of approximately 300 square miles and enters the Pacific Ocean west of the village of Petrolia, California and is located at the northern end of the King Range National Conservation Area. The project area consists of a wide alluvial river with simplified instream habitat, shallow pools, and scarce stream-side vegetation. The river channel migrates frequently, resulting in rapid turnover of mid-channel islands. Due to tectonic uplift and river channel migration the large slough network on the south side of the river is disconnected during most flow conditions. Currently, summer habitat conditions in the lower river and estuary are generally poor for juvenile Pacific salmon. The area is broad, shallow, and lacks areas for fish to hide from predators with summer water temperatures in the lower river regularly exceeding levels thought to be stressful, and even lethal, to Pacific salmonids.


Project Description: As shown in attachment 2, the applicant proposes to perform a variety of stream restoration and aquatic habitat improvement activities including the placement of up to 40 large wood structures, installation of up to 15,000 linear feet of willow baffles, and construction of up to 4,800-ft of slough channel. The slough channel excavations will be approximately 30 to 50-ft wide and up to 10-ft deep. Trenches for the willow baffles will be excavated, and subsequently back filled, approximately 15-ft deep and 3-ft wide on river terrace margins and mid-channel islands.


Basic Project Purpose: The basic project purpose comprises the fundamental, essential, or irreducible purpose of the project, and is used by USACE to determine whether the project is water dependent. The basic project purpose is to restore and enhance estuary and instream aquatic habitat for salmonids.


Overall Project Purpose: The overall project purpose serves as the basis for the Section 404(b)(1) alternatives analysis and is determined by further defining the basic project purpose in a manner that more specifically describes the applicant's goals for the project while allowing a reasonable range of alternatives to be analyzed. The overall project purpose is to improve juvenile salmonid survival during summer low-flow periods and increase winter habitat for fish.


Project Impacts: The applicant proposes to impact approximately 3 miles of Section 10 and Section 404 waters. Permanent impacts include placement of fill material for fish habitat structures and will be comprised of wood, plant material, and rocks spread over approximately 1 acre and amounting to approximately 3,140 cubic yards. Temporary impacts consist of approximately 10 cubic yards of river gravel spread over 200 square feet for the installation of culverts necessary for equipment access.


Proposed Mitigation: The proposed project consists entirely of restoration activities and therefore no mitigation is proposed.


3. STATE AND LOCAL APPROVALS:


Water Quality Certification: State water quality certification or a waiver thereof is a prerequisite for the issuance of a Department of the Army Permit to conduct any activity which may result in a fill or pollutant discharge into waters of the United States, pursuant to Section 401 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1341 et seq.). The applicant has recently submitted an application to the California Regional Water Quality Control Board (RWQCB) to obtain water quality certification for the project. No Department of the Army Permit will be issued until the applicant obtains the required certification or a waiver of certification. A waiver can be explicit, or it may be presumed if the RWQCB fails or refuses to act on a complete application for water quality certification within 60 days of receipt, unless the District Engineer determines a shorter or longer period is a reasonable time for the RWQCB to act.


Water quality issues should be directed to the Executive Officer, California Regional Water Quality Control Board, North Coast Region, 5550 Skylane Boulevard, Suite A, Santa Rosa, California 95403, by the close of the comment period.


Coastal Zone Management: Section 307(c) of the Coastal Zone Management Act of 1972, as amended (16 U.S.C. § 1456(c) et seq.), requires a non-Federal applicant seeking a federal license or permit to conduct any activity occurring in or affecting the coastal zone to obtain a Consistency Certification that indicates the activity conforms with the state’s coastal zone management program. Generally, no federal license or permit will be granted until the appropriate state agency has issued a Consistency Certification or has waived its right to do so. Section 307(c) of the Coastal Zone Management Act of 1972, as amended (16 U.S.C. § 1456(c) et seq.), requires a Federal applicant seeking a federal license or permit to conduct any activity occurring in or affecting the coastal zone to obtain a Consistency Determination that indicates the activity conforms with the state’s coastal zone management program. Generally, no federal license or permit will be granted until the appropriate state agency has issued a Consistency Determination or has waived its right to do so. Since the project occurs in the coastal zone the applicant has applied for and received concurrence on their negative determination from the California Coastal Commission North Coast Office.


Coastal zone management issues should be directed to the District Manager, California Coastal Commission, North Coast District Office, 1385 8th street, Arcata, CA by the close of the comment period.


4. COMPLIANCE WITH VARIOUS FEDERAL LAWS:


National Environmental Policy Act (NEPA): Upon review of the Department of the Army permit application and other supporting documentation, USACE has made a preliminary determination that the project neither qualifies for a Categorical Exclusion nor requires the preparation of an Environmental Impact Statement for the purposes of NEPA. At the conclusion of the public comment period, USACE will assess the environmental impacts of the project in accordance with the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. §§ 4321-4347), the Council on Environmental Quality's regulations at 40 C.F.R. § 1500‑1508, and USACE regulations at 33 C.F.R. § 325. The final NEPA analysis will normally address the direct, indirect, and cumulative impacts that result from regulated activities within the jurisdiction of USACE and other non-regulated activities USACE determines to be within its purview of Federal control and responsibility to justify an expanded scope of analysis for NEPA purposes. The final NEPA analysis will be incorporated in the decision documentation that provides the rationale for issuing or denying a Department of the Army Permit for the project. The final NEPA analysis and supporting documentation will be on file with the San Francisco District, Regulatory Division.


Endangered Species Act (ESA): Section 7(a)(2) of the ESA or 1973, as amended (16 U.S.C. § 1531 et seq.), requires Federal agencies to consult with either the U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries Service (NMFS) to ensure actions authorized, funded, or undertaken by the agency are not likely to jeopardize the continued existence of any Federally-listed species or result in the adverse modification of designated critical habitat. As the Federal lead agency for this project, the applicant will be responsible for determining the presence or absence of Federally-listed species and designated critical habitat and the need to conduct consultation. To complete the administrative record and the decision on whether to issue a Department of the Army Permit for the project, USACE will obtain all necessary supporting documentation from the applicant concerning the consultation process. Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project.


Magnuson-Stevens Fishery Conservation and Management Act (MSFCMA): Section 305(b)(2) of the MSFCMA of 1966, as amended (16 U.S.C. § 1801 et seq.), requires Federal agencies to consult with the National Marine Fisheries Service (NMFS) on all proposed actions authorized, funded, or undertaken by the agency that may adversely affect essential fish habitat (EFH). EFH is defined as those waters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity. EFH is designated only for those species managed under a Federal Fisheries Management Plan (FMP), such as the Pacific Groundfish FMP, the Coastal Pelagics FMP, orthe Pacific Coast Salmon FMP. As the Federal lead agency for this project, the applicant will be responsible for determining the presence or absence of EFH and the need to conduct consultation. To complete the administrative record and the decision on whether to issue a Department of the Army Permit for the project, USACE will obtain all necessary supporting documentation from the applicant concerning the consultation process. Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project.


Marine Protection, Research, and Sanctuaries Act (MPRSA): Section 302 of the MPRSA of 1972, as amended (16 U.S.C. § 1432 et seq.), authorizes the Secretary of Commerce, in part, to designate areas of ocean waters, such as the Cordell Bank, Gulf of the Farallones, and Monterey Bay, as National Marine Sanctuaries for the purpose of preserving or restoring such areas for their conservation, recreational, ecological, or aesthetic values. After such designation, activities in sanctuary waters authorized under other authorities are valid only if the Secretary of Commerce certifies that the activities are consistent with Title III of the Act. No Department of the Army Permit will be issued until the applicant obtains any required certification or permit. The project does not occur in sanctuary waters, and a preliminary review by USACE indicates the project is not likely to affect sanctuary resources. This presumption of effect, however, remains subject to a final determination by the Secretary of Commerce or his designee.


National Historic Preservation Act (NHPA): Section 106 of the NHPA of 1966, as amended (16 U.S.C. § 470 et seq.), requires Federal agencies to consult with the appropriate State Historic Preservation Officer to take into account the effects of their undertakings on historic properties listed in or eligible for listing in the National Register of Historic Places. Section 106 of the Act further requires Federal agencies to consult with the appropriate Tribal Historic Preservation Officer or any Indian tribe to take into account the effects of their undertakings on historic properties, including traditional cultural properties, trust resources, and sacred sites, to which Indian tribes attach historic, religious, and cultural significance. As the Federal lead agency for this undertaking, USACE has conducted a review of the latest published version of the National Register of Historic Places, survey information on file with various city and county municipalities, and other information provided by the applicant to determine the presence or absence of historic and archaeological resources within the permit area. Based on this review, USACE has made a preliminary determination that historic or archaeological resources are not likely to be present in the permit area and that the project either has no potential to cause effects to these resources or has no effect to these resources. USACE will render a final determination on the need for consultation at the close of the comment period, taking into account any comments provided by the State Historic Preservation Officer, the Tribal Historic Preservation Officer, the Advisory Council on Historic Preservation, and Native American Nations or other tribal governments. If unrecorded archaeological resources are discovered during project implementation, those operations affecting such resources will be temporarily suspended until USACE concludes Section 106 consultation with the State Historic Preservation Officer or the Tribal Historic Preservation Officer to take into account any project related impacts to those resources.


5. COMPLIANCE WITH THE SECTION 404(b)(1) GUIDELINES:


Projects resulting in discharges of dredged or fill material into waters of the United States must comply with the Guidelines promulgated by the Administrator of the Environmental Protection Agency under Section 404(b) of the Clean Water Act (33 U.S.C. § 1344(b)). An evaluation pursuant to the Guidelines indicates the project is dependent on location in or proximity to waters of the United States to achieve the basic project purpose. This conclusion raises the (rebuttable) presumption of the availability of a practicable alternative to the project that would result in less adverse impacts to the aquatic ecosystem while not causing other major adverse environmental consequences. The applicant has been informed to submit an analysis of project alternatives to be reviewed for compliance with the Guidelines.


6. PUBLIC INTEREST EVALUTION:


The decision on whether to issue a Department of the Army Permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the project and its intended use on the public interest. Evaluation of the probable impacts requires a careful weighing of the public interest factors relevant in each particular case. The benefits that may accrue from the project must be balanced against any reasonably foreseeable detriments of project implementation. The decision on permit issuance will, therefore, reflect the national concern for both protection and utilization of important resources. Public interest factors which may be relevant to the decision process include conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people.


7. CONSIDERATION OF COMMENTS:


USACE is soliciting comments from the public; Federal, State, and local agencies and officials; Native American Nations or other tribal governments; and other interested parties in order to consider and evaluate the impacts of the project. All comments received by USACE will be considered in the decision on whether to issue, modify, condition, or deny a Department of the Army Permit for the project. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, and other environmental or public interest factors addressed in a final environmental assessment or environmental impact statement. Comments are also used to determine the need for a public hearing and to determine the overall public interest in the project.


8. SUBMITTING COMMENTS:


During the specified comment period, interested parties may submit written comments to L. Kasey Sirkin, San Francisco District, Regulatory Division, Eureka Field Office, 601 Startare Drive, Box 14, Eureka, California 95501; comment letters should cite the project name, applicant name, and public notice number to facilitate review by the Regulatory Permit Manager. Comments may include a request for a public hearing on the project prior to a determination on the Department of the Army permit application; such requests shall state, with particularity, the reasons for holding a public hearing. All substantive comments will be forwarded to the applicant for resolution or rebuttal. Additional project information or details on any subsequent project modifications of a minor nature may be obtained from the applicant and/or agent or by contacting the Regulatory Permit Manager by telephone or e-mail (cited in the public notice letterhead. An electronic version of this public notice may be viewed under the Public Notices tab on the USACE website: http://www.spn.usace.army.mil/Missions/Regulatory.



Regulatory Links

Redirecting...

Contact Information

Department of the Army
San Francisco District, Corps of Engineers
Regulatory Division
450 Golden Gate Ave., 4th Floor
San Francisco, California 94102-3404

Phone Number: (415) 503-6795
Fax Number: (415) 503-6693
cespn-regulatory-info@usace.army.mil