Regulatory Public Notices

Collapse All Expand All
 - WE ENCOURAGE YOUR COMMENTS -

Under the Corps' Regulatory Program, a public notice is the primary method for advising all interested parties of a proposed activity for which a permit is sought. Public notices are also published to inform the public about new or proposed regulations, policies, guidance or permit procedures.

We are requesting public comments on many Public Notices (PNs) concurrently; please pay careful attention to the file number and the comments Due Date.

Email comments are preferred.  To submit comments in writing, send them to the attention of the Project Manager listed in the Public Notice title block.  All comments should reference the PN file number and be submitted by the Response Required Date on the PN.


The Public Notices are in pdf format. To read the files you may need to download and install Adobe Acrobat Reader or another comparable program

 Receive Regulatory Program Public Notices

If you would like to be added to one or more of the public notice mailing lists, send an email to cespn-rg-info@usace.army.mil with your contact information (Name, Organization, Mailing Address, Email, Phone Number) and the notification list(s) you would like to be added to:

All Counties within San Francisco District 
- or -
Alameda  |  Contra Costa  |  Del Norte  |  Humboldt  |  Marin  |  Mendocino
Monterey  |  Napa  |  San Benito  |  San Francisco  |  San Luis Obispo  |  San Mateo
Santa Clara  |  Santa Cruz  |  Siskiyou  |  Solano  |  Sonoma  |  Trinity

 


If you are on our mailing list and your contact information changes, please notify cespn-rg-info@usace.army.mil with your new addresses.  E-mails returned due to a non-functioning address will be removed from notification lists.

SPN-2008-00283 Riverview Apartments Project

Published June 18, 2020
Expiration date: 7/18/2020

PROJECT: Riverview Apartments Project

PUBLIC NOTICE NUMBER:  SPN-2008-00283
PUBLIC NOTICE DATE:  June 18, 2020
COMMENTS DUE DATE:  July 18, 2020
PERMIT MANAGER: Bryan Matsumoto  |  TELEPHONE:  415-503-6786  |  E-MAIL: Bryan.T.Matsumoto@usace.army.mil


1.         INTRODUCTION:  Baywood LLC (POC: Patrick Imbimbo, 707-578-5344), 414 Aviation Boulevard, Santa Rosa, California 95403, through its agent, WRA, Inc. (POC: Douglas Spicher, 707-283-5673), 5341 Old Redwood Highway, Petaluma, California 94954, has applied to the U.S. Army Corps of Engineers (USACE), San Francisco District, for a Department of the Army Permit to discharge fill material into jurisdictional waters of the United States associated with the construction of a residential subdivision, located in the City of Petaluma, Sonoma County, California.  This Department of the Army permit application is being processed pursuant to the provisions of Section 404 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1344 et seq.).

2.         PROPOSED PROJECT:

Project Site Location: The approximately 14.45-acre project site is located at the terminus of Casa Grande Road, south of State Highway 116, northwest of Adobe Creek, northeast of the Petaluma River, and east of Highway 101 in the City of Petaluma, Sonoma County, California (APNs 005-060-041 and -042, Lat: 38.230°, Long: -122.605°) (Figure 1).

Project Site Description: The project site, now vacant, was most recently the site of a soap factory facility.  Land uses around the project site include a dog park to the west, apartment house to the north, a light industrial complex to the east, and open space to the south.  The site gently slopes to the southwest, with drainage flowing into the Petaluma River.  The dominant plant community on the project site is ruderal/non-native grassland (10.66 acres), followed by wetlands (2.15 acres), stock pile (1.63 acres), and other waters of the U.S. (0.01 acre), which is underlain by both Clear Lake and Reyes Silty Clay soils.

Project Description:  As shown in the attached drawings, the applicant proposes to construct 27 buildings, resulting in 264 apartment housing units.  The project would include associated features, such as parking areas, management office/recreation building, recreation areas, along with streets, driveways, sidewalks, and landscaped open areas (Figure 2).  Additional work on the site includes soil remediation within and outside of wetland areas. 

Basic Project Purpose: The basic project purpose comprises the fundamental, essential, or irreducible purpose of the project, and is used by USACE to determine whether the project is water dependent. The basic project purpose is to construct high-density residential housing.

Overall Project Purpose:  The overall project purpose serves as the basis for the Section 404(b)(1) alternatives analysis and is determined by further defining the basic project purpose in a manner that more specifically describes the applicant's goals for the project while allowing a reasonable range of alternatives to  be analyzed.  The overall project purpose is to construct a high-density residential development in an infill location in the City of Petaluma close to existing services, transportation, work opportunities, schools, and recreation, which will help to alleviate urgent housing needs, and is consistent with the City of Petaluma General Plan.

Project Impacts: Construction of the proposed project would result in impacts to 1.67 acres of wetlands.  Excavation of heavy metal contaminated soils account for 0.49 acre of wetlands impacts, which would be backfilled with clean fill and 0.13 acre of wetlands returned to pre-excavation contours.  In addition, 1.17 acres of wetlands, and 0.01 acre of other waters would be permanently impacted through site grading/leveling for preparation of the site for the development. 

Proposed Mitigation: To mitigate for permanent impacts to 1.53 acres of wetlands, 0.01 acre of other waters, and temporary impacts to 0.13 acre of wetlands, the applicant has proposed a combination of onsite wetlands restoration/preservation, and offsite wetland establishment. 

On the project site, the applicant would restore and preserve 0.13 acre of wetlands to pre-excavation contours after soil remediation.  Offsite mitigation is proposed at an abandoned golf course approximately 1.9 miles northeast of the project site along Adobe Creek (See Figure 1).  Establishment of 3.21 acre of wetlands would be completed at the site (Figure 3). 

Project Alternatives: USACE has not endorsed the submitted alternatives analysis at this time. USACE will conduct an independent review of the project alternatives prior to reaching a final permit decision.

3.         STATE AND LOCAL APPROVALS:

Water Quality Certification: State water quality certification or a waiver thereof is a prerequisite for the issuance of a Department of the Army Permit to conduct any activity which may result in a fill or pollutant discharge into waters of the United States, pursuant to Section 401 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1341 et seq.).  The applicant has recently submitted an application to the California Regional Water Quality Control Board (RWQCB) to obtain water quality certification for the project.  No Department of the Army Permit will be issued until the applicant obtains the required certification or a waiver of certification.  A waiver can be explicit, or it may be presumed if the RWQCB fails or refuses to act on a complete application for water quality certification within 60 days of receipt, unless the District Engineer determines a shorter or longer period is a reasonable time for the RWQCB to act.

Water quality issues should be directed to the Executive Officer, California Regional Water Quality Control Board, San Francisco Bay Region, 1515 Clay Street, Suite 1400, Oakland, California 94612, by the close of the comment period. 

Coastal Zone Management: Section 307(c) of the Coastal Zone Management Act of 1972, as amended (16 U.S.C. § 1456(c) et seq.), requires a non-Federal applicant seeking a federal license or permit to conduct any activity occurring in or affecting the coastal zone to obtain a Consistency Certification that indicates the activity conforms with the state’s coastal zone management program.  Generally, no federal license or permit will be granted until the appropriate state agency has issued a Consistency Certification or has waived its right to do so.  The project does not occur in the coastal zone, and a preliminary review by USACE indicates the project is not likely to affect coastal zone resources.  This presumption of effect, however, remains subject to a final determination by the San Francisco Bay Conservation and Development Commission.

Coastal zone management issues should be directed to the Executive Director, San Francisco Bay Conservation and Development Commission, 375 Beale St., Suite 510, San Francisco, CA  94105, by the close of the comment period.

4.         COMPLIANCE WITH VARIOUS FEDERAL LAWS:

National Environmental Policy Act (NEPA):  Upon review of the Department of the Army permit application and other supporting documentation, USACE has made a preliminary determination that the project neither qualifies for a Categorical Exclusion nor requires the preparation of an Environmental Impact Statement for the purposes of NEPA.  At the conclusion of the public comment period, USACE will assess the environmental impacts of the project in accordance with the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. §§ 4321-4347), the Council on Environmental Quality's regulations at 40 C.F.R. § 1500‑1508, and USACE regulations at 33 C.F.R. § 325.  The final NEPA analysis will normally address the direct, indirect, and cumulative impacts that result from regulated activities within the jurisdiction of USACE and other non-regulated activities USACE determines to be within its purview of Federal control and responsibility to justify an expanded scope of analysis for NEPA purposes. The final NEPA analysis will be incorporated in the decision documentation that provides the rationale for issuing or denying a Department of the Army Permit for the project. The final NEPA analysis and supporting documentation will be on file with the San Francisco District, Regulatory Division. 

Endangered Species Act (ESA):  Section 7(a)(2) of the ESA of 1973, as amended (16 U.S.C. § 1531 et seq.), requires Federal agencies to consult with either the U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries Service (NMFS) to ensure actions authorized, funded, or undertaken by the agency are not likely to jeopardize the continued existence of any Federally-listed species or result in the adverse modification of designated critical habitat.  As the Federal lead agency for this project, USACE has conducted a review of the California Natural Diversity Data Base, digital maps prepared by USFWS and NMFS depicting critical habitat, and other information provided by the applicant to determine the presence or absence of such species and critical habitat in the project area.  Based on this review, USACE has made a preliminary determination that the following Federally-listed species are present at the project location or in its vicinity and may be affected by project implementation: salt-marsh harvest mouse (Reithrodontomys raviventris), California Ridgway’s rail (Rallus obsoletus obsoletus), and California red-legged frog (Rana draytonii).  To address project related impacts to these species, USACE will initiate formal consultation with USFWS, pursuant to Section 7(a) of the Act.  Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project.

Magnuson-Stevens Fishery Conservation and Management Act (MSFCMA):  Section 305(b)(2) of the MSFCMA of 1966, as amended (16 U.S.C. § 1801 et seq.), requires Federal agencies to consult with the NMFS on all proposed actions authorized, funded, or undertaken by the agency that may adversely affect essential fish habitat (EFH). EFH is defined as those waters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity.  EFH is designated only for those species managed under a Federal Fisheries Management Plan (FMP), such as the Pacific Groundfish FMP, the Coastal Pelagics FMP, or the Pacific Coast Salmon FMP.  As the Federal lead agency for this project, USACE has conducted a review of digital maps prepared by NMFS depicting EFH to determine the presence or absence of EFH in the project area.  Based on this review, USACE has made a preliminary determination that EFH is present at the project location or in its vicinity and that the critical elements of EFH would not be adversely affected by project implementation.    

Marine Protection, Research, and Sanctuaries Act (MPRSA):  Section 302 of the MPRSA of 1972, as amended (16 U.S.C. § 1432 et seq.), authorizes the Secretary of Commerce, in part, to designate areas of ocean waters, such as the Cordell Bank, Gulf of the Farallones, and Monterey Bay, as National Marine Sanctuaries for the purpose of preserving or restoring such areas for their conservation, recreational, ecological, or aesthetic values. After such designation, activities in sanctuary waters authorized under other authorities are valid only if the Secretary of Commerce certifies that the activities are consistent with Title III of the Act.  No Department of the Army Permit will be issued until the applicant obtains any required certification or permit.  The project does not occur in sanctuary waters, and a preliminary review by USACE indicates the project is not likely to affect sanctuary resources.  This presumption of effect, however, remains subject to a final determination by the Secretary of Commerce or his designee.

National Historic Preservation Act (NHPA):  Section 106 of the NHPA of 1966, as amended (16 U.S.C. § 470 et seq.), requires Federal agencies to consult with the appropriate State Historic Preservation Officer to take into account the effects of their undertakings on historic properties listed in or eligible for listing in the National Register of Historic Places.  Section 106 of the Act further requires Federal agencies to consult with the appropriate Tribal Historic Preservation Officer or any Indian tribe to take into account the effects of their undertakings on historic properties, including traditional cultural properties, trust resources, and sacred sites, to which Indian tribes attach historic, religious, and cultural significance.  As the Federal lead agency for this undertaking, USACE has conducted a review of the latest published version of the National Register of Historic Places, survey information on file with various city and county municipalities, and other information provided by the applicant to determine the presence or absence of historic and archaeological resources within the permit area.  Based on this review, USACE has made a preliminary determination that historic or archaeological resources are not likely to be present in the permit area and that the project has no effect to these resources.  USACE will render a final determination on the need for consultation at the close of the comment period, taking into account any comments provided by the State Historic Preservation Officer, the Tribal Historic Preservation Officer, the Advisory Council on Historic Preservation, and Native American Nations or other tribal governments.  To address project related impacts to historic or archaeological resources, USACE will initiate consultation with the State Historic Preservation Officer or the Tribal Historic Preservation Officer, pursuant to Section 106 of the Act.  Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project.

5.         COMPLIANCE WITH THE SECTION 404(b)(1) GUIDELINES: Projects resulting in discharges of dredged or fill material into waters of the United States must comply with the Guidelines promulgated by the Administrator of the Environmental Protection Agency under Section 404(b) of the Clean Water Act (33 U.S.C. § 1344(b)).  An evaluation pursuant to the Guidelines indicates the project is not dependent on location in or proximity to waters of the United States to achieve the basic project purpose.  This conclusion raises the (rebuttable) presumption of the availability of a less environmentally damaging practicable alternative to the project that does not require the discharge of dredged or fill material into special aquatic sites.  The applicant has submitted an analysis of project alternatives which is being reviewed by USACE.

6.         PUBLIC INTEREST EVALUTION:  The decision on whether to issue a Department of the Army Permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the project and its intended use on the public interest. Evaluation of the probable impacts requires a careful weighing of the public interest factors relevant in each particular case.  The benefits that may accrue from the project must be balanced against any reasonably foreseeable detriments of project implementation.  The decision on permit issuance will, therefore, reflect the national concern for both protection and utilization of important resources.  Public interest factors which may be relevant to the decision process include conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people.

7.         CONSIDERATION OF COMMENTS:  USACE is soliciting comments from the public; Federal, State, and local agencies and officials; Native American Nations or other tribal governments; and other interested parties in order to consider and evaluate the impacts of the project.  All comments received by USACE will be considered in the decision on whether to issue, modify, condition, or deny a Department of the Army Permit for the project.  To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, and other environmental or public interest factors addressed in a final environmental assessment or environmental impact statement.  Comments are also used to determine the need for a public hearing and to determine the overall public interest in the project.

8.         SUBMITTING COMMENTS:  During the specified comment period, interested parties may submit written comments to Bryan Matsumoto, San Francisco District, Regulatory Division, 450 Golden Gate Avenue, 4th Floor, Suite 1111, San Francisco, California 94102-3404, or by e-mail; comments should cite the project name, applicant name, and public notice number to facilitate review by the Regulatory Permit Manager.  Comments may include a request for a public hearing on the project prior to a determination on the Department of the Army permit application; such requests shall state, with particularity, the reasons for holding a public hearing.  All substantive comments will be forwarded to the applicant for resolution or rebuttal.  Additional project information or details on any subsequent project modifications of a minor nature may be obtained from the applicant and/or agent or by contacting the Regulatory Permit Manager by telephone or e-mail (cited in the public notice letterhead).  An electronic version of this public notice may be viewed under the Public Notices tab on the USACE website:  https://www.spn.usace.army.mil/Missions/Regulatory.


Regulatory Links

Redirecting...

Contact Information

Department of the Army
San Francisco District, Corps of Engineers
Regulatory Division
450 Golden Gate Ave., 4th Floor
San Francisco, California 94102-3404

Phone Number: (415) 503-6795
Fax Number: (415) 503-6693
cespn-regulatory-info@usace.army.mil