 - WE ENCOURAGE YOUR COMMENTS -

Under the Corps' Regulatory Program, a public notice is the primary method for advising all interested parties of a proposed activity for which a permit is sought. Public notices are also published to inform the public about new or proposed regulations, policies, guidance or permit procedures.

We are requesting public comments on many Public Notices (PNs) concurrently; please pay careful attention to the file number and the comments Due Date.

Email comments are preferred.  To submit comments in writing, send them to the attention of the Project Manager listed in the Public Notice title block.  All comments should reference the PN file number and be submitted by the Response Required Date on the PN.


The Public Notices are in pdf format. To read the files you may need to download and install Adobe Acrobat Reader or another comparable program

 Receive Regulatory Program Public Notices

If you would like to be added to one or more of the public notice mailing lists, send an email to cespn-rg-info@usace.army.mil with your contact information (Name, Organization, Mailing Address, Email, Phone Number) and the notification list(s) you would like to be added to:

All Counties within San Francisco District 
- or -
Alameda  |  Contra Costa  |  Del Norte  |  Humboldt  |  Marin  |  Mendocino
Monterey  |  Napa  |  San Benito  |  San Francisco  |  San Luis Obispo  |  San Mateo
Santa Clara  |  Santa Cruz  |  Siskiyou  |  Solano  |  Sonoma  |  Trinity

 


If you are on our mailing list and your contact information changes, please notify cespn-rg-info@usace.army.mil with your new addresses.  E-mails returned due to a non-functioning address will be removed from notification lists.

2001-265570N Residences at Napa Junction

RGS
Published April 13, 2023
Expiration date: 5/13/2023

PROJECT: Residences at Napa Junction

PUBLIC NOTICE NUMBER: 2001-265570N

PUBLIC NOTICE DATE: April 13, 2023

COMMENTS DUE DATE: May 13, 2023

PROJECT MANAGER: Keith Hess                                             TELEPHONE: 707-443-0855                            E-MAIL: keith.d.hess@usace.army.mil


INTRODUCTION: American Canyon Ventures LLC (POC: Mr. Scott Mendelsohn 415-408-1962), 516 Oak Vista Court, Santa Rosa, California, 95409, through its agent, Gillenwater Consulting, LLC (POC: Daniel Gillenwater 435-647-6427), 5667 Kingsford Avenue, Park City, Utah, 84098, has applied to the U.S. Army Corps of Engineers (USACE), San Francisco District, for a Department of the Army Permit to discharge fill material into jurisdictional waters of the United States associated with the construction of a residential subdivision, located on an undeveloped parcel within American Canyon, Napa County, California. This Department of the Army permit application is being processed pursuant to the provisions of Section 404 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1344 et seq.).

PROPOSED PROJECT:

Project Site Location: Approximately 0.5 miles north of 658 Napa Junction Road, within the City of American Canyon, Napa County, California, at latitude  38.187641° N, longitude -122.252536°W.

Project Site Description: The proposed 15.05-acre residential development is located on an undeveloped property along the east end of Napa Junction Road that was formerly associated with the California Northern Railroad Lombard Railyard and was utilized by the Southern Pacific Railroad. The site contains seasonal wetlands (1.438 acres) and Other Waters of the U.S. (0.084 acres) which are tributary to North Slough, tributary to San Pablo Bay. The proposed project area is bounded by residential and commercial development to the north and south, Highway 29 to the west, and the Southern Pacific Rail line to the east.

Project Description: As shown in the attached drawings, the applicant proposes to construct 453 residential rental units, a community center with both indoor and outdoor amenities, and associated circulation and parking infrastructure within 13.44 acres of the 15.05-acre property. The remaining 1.61 acres of property would be retained as open space to preserve existing seasonal wetlands, create new seasonal wetlands, and provide passive recreation amenities for residents of the development. Construction of the development pursuant to the preliminary grading plan will result in approximately 11,437 cubic yards of fill that would result in permanent impacts to approximately 0.986 acres of seasonal wetlands and 0.028 acre of Other Waters of the U.S. (OWUS).

Basic Project Purpose: The basic project purpose comprises the fundamental, essential, or irreducible purpose of the project, and is used by USACE to determine whether the project is water dependent. The basic project purpose is to construct rental units to provide for housing.

Overall Project Purpose: The overall project purpose serves as the basis for the Section 404(b)(1) alternatives analysis and is determined by further defining the basic project purpose in a manner that more specifically describes the applicant's goals for the project while allowing a reasonable range of alternatives to be analyzed. The overall project purpose is to provide affordable rental housing within the Broadway District Specific Plan (BDSP) area within American Canyon.

Project Impacts: Permanent impacts would occur within 0.986 acres of seasonal wetlands and 0.028 acres of OWUS from grading activities resulting in the discharge of approximately 11,437 cubic yards of fill.

Proposed Mitigation: Permanent impacts to seasonal wetlands and OWUS as a result of project construction would be mitigated for through a combination of on-site permittee-responsible and off-site compensatory mitigation (wetland and OWUS creation and restoration). The applicant will develop a mitigation, Monitoring, and Reporting Plan (MMRP) detailing the mitigation strategy with input and guidance from the Corps, however, the use of an appropriate mitigation bank is also being examined as an alternative.

The applicant has proposed avoidance and minimization measures within the strategy and design of the proposed project that include: requesting waivers from the City’s design standards to reduce to project footprint; locating staging areas within upland areas; fencing off aquatic resources; providing training for contractors; providing on-site biological monitors; and implementation of erosion control BMPs.

Project Alternatives: USACE has not endorsed an alternatives analysis at this time. USACE will conduct an independent review of the project alternatives prior to reaching a final permit decision.

STATE AND LOCAL APPROVALS:

Water Quality Certification: State water quality certification or a waiver thereof is a prerequisite for the issuance of a Department of the Army Permit to conduct any activity which may result in a fill or pollutant discharge into waters of the United States, pursuant to Section 401 of the Clean Water Act of 1972, as amended (33 U.S.C. § 1341 et seq.). The applicant has recently submitted an application to the California Regional Water Quality Control Board (RWQCB) to obtain water quality certification for the project. No Department of the Army Permit will be issued until the applicant obtains the required certification or a waiver of certification. A waiver can be explicit, or it may be presumed if the RWQCB fails or refuses to act on a complete application for water quality certification within 60 days of receipt, unless the District Engineer determines a shorter or longer period is a reasonable time for the RWQCB to act.

Water quality issues should be directed to the Executive Officer, California Regional Water Quality Control Board, North Coast Region, 5550 Skylane Boulevard, Suite A, Santa Rosa, California 95403, by the close of the comment period.

Coastal Zone Management: The project does not occur in the coastal zone, and a preliminary review by USACE indicates the project is not likely to affect coastal zone resources. This presumption of effect, however, remains subject to a final determination by the California Coastal Commission.

Other Local Approvals: The applicant will be applying for the following additional governmental authorizations for the project: A Lake and Streambed Alteration Agreement to be issued by the California Fish and Wildlife Department.

COMPLIANCE WITH VARIOUS FEDERAL LAWS:

National Environmental Policy Act (NEPA): Upon review of the Department of the Army permit application and other supporting documentation, USACE has made a preliminary determination that the project neither qualifies for a Categorical Exclusion nor requires the preparation of an Environmental Impact Statement for the purposes of NEPA. At the conclusion of the public comment period, USACE will assess the environmental impacts of the project in accordance with the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. §§ 4321-4347), the Council on Environmental Quality's regulations at 40 C.F.R. § 1500‑1508, and USACE regulations at 33 C.F.R. § 325. The final NEPA analysis will normally address the direct, indirect, and cumulative impacts that result from regulated activities within the jurisdiction of USACE and other non-regulated activities USACE determines to be within its purview of Federal control and responsibility to justify an expanded scope of analysis for NEPA purposes. The final NEPA analysis will be incorporated in the decision documentation that provides the rationale for issuing or denying a Department of the Army Permit for the project. The final NEPA analysis and supporting documentation will be on file with the San Francisco District, Regulatory Division.

Endangered Species Act (ESA): Section 7(a)(2) of the ESA or 1973, as amended (16 U.S.C. § 1531 et seq.), requires Federal agencies to consult with either the U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries Service (NMFS) to ensure actions authorized, funded, or undertaken by the agency are not likely to jeopardize the continued existence of any Federally-listed species or result in the adverse modification of designated critical habitat. As the Federal lead agency for this project, USACE has conducted a review of the California Natural Diversity Data Base, digital maps prepared by USFWS and NMFS depicting critical habitat, and other information provided by the applicant to determine the presence or absence of such species and critical habitat in the project area. Based on this review, USACE has made a preliminary determination that the following Federally-listed species are present at the project location or in its vicinity and may be affected by project implementation. The federally listed California Red-legged frog (Rana draytonii) and two-fork clover (Trifolium amoenum) are known to have historically occurred within the vicinity of the project area.  To address project related impacts to these species, USACE will initiate informal consultation with USFWS, pursuant to Section 7(a) of the Act. Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project.

Magnuson-Stevens Fishery Conservation and Management Act (MSFCMA): Section 305(b)(2) of the MSFCMA of 1966, as amended (16 U.S.C. § 1801 et seq.), requires Federal agencies to consult with the National Marine Fisheries Service (NMFS) on all proposed actions authorized, funded, or undertaken by the agency that may adversely affect essential fish habitat (EFH). EFH is defined as those waters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity. EFH is designated only for those species managed under a Federal Fisheries Management Plan (FMP), such as the Pacific Groundfish FMP, the Coastal Pelagics FMP, or the Pacific Coast Salmon FMP. Based on this review, USACE has made a preliminary determination that EFH is not present at the project location or in its vicinity and that consultation will not be required. USACE will render a final determination on the need for consultation at the close of the comment period, taking into account any comments provided by NMFS.

Marine Protection, Research, and Sanctuaries Act (MPRSA): Section 302 of the MPRSA of 1972, as amended (16 U.S.C. § 1432 et seq.), authorizes the Secretary of Commerce, in part, to designate areas of ocean waters, such as the Cordell Bank, Gulf of the Farallones, and Monterey Bay, as National Marine Sanctuaries for the purpose of preserving or restoring such areas for their conservation, recreational, ecological, or aesthetic values. After such designation, activities in sanctuary waters authorized under other authorities are valid only if the Secretary of Commerce certifies that the activities are consistent with Title III of the Act. No Department of the Army Permit will be issued until the applicant obtains any required certification or permit. The project does not occur in sanctuary waters, and a preliminary review by USACE indicates the project is not likely to affect sanctuary resources. This presumption of effect, however, remains subject to a final determination by the Secretary of Commerce or his designee.

National Historic Preservation Act (NHPA): Section 106 of the NHPA of 1966, as amended (16 U.S.C. § 470 et seq.), requires Federal agencies to consult with the appropriate State Historic Preservation Officer to take into account the effects of their undertakings on historic properties listed in or eligible for listing in the National Register of Historic Places. Section 106 of the Act further requires Federal agencies to consult with the appropriate Tribal Historic Preservation Officer or any Indian tribe to take into account the effects of their undertakings on historic properties, including traditional cultural properties, trust resources, and sacred sites, to which Indian tribes attach historic, religious, and cultural significance. As the Federal lead agency for this undertaking, USACE has conducted a review of the latest published version of the National Register of Historic Places, survey information on file with various city and county municipalities, and other information provided by the applicant to determine the presence or absence of historic and archaeological resources within the permit area.  USACE will render a final determination on the need for consultation at the close of the comment period, taking into account any comments provided by the State Historic Preservation Officer, the Tribal Historic Preservation Officer, the Advisory Council on Historic Preservation, and Native American Nations or other tribal governments. Based on this review, USACE has made a preliminary determination that historic or archaeological resources are present in the permit area and that such resources may be adversely affected by the project. The records provided by the applicant identify historic resources associated with the “ca.1925 Southern Pacific balloon loop”, that may be physically altered as a result of the proposed project.   To address project related impacts to historic or archaeological resources, USACE will initiate consultation with the State Historic Preservation Officer or the Tribal Historic Preservation Officer, pursuant to Section 106 of the Act. Any required consultation must be concluded prior to the issuance of a Department of the Army Permit for the project. If unrecorded archaeological resources are discovered during project implementation, those operations affecting such resources will be temporarily suspended until USACE concludes Section 106 consultation with the State Historic Preservation Officer or the Tribal Historic Preservation Officer to take into account any project related impacts to those resources.

COMPLIANCE WITH THE SECTION 404(b)(1) GUIDELINES: Projects resulting in discharges of dredged or fill material into waters of the United States must comply with the Guidelines promulgated by the Administrator of the Environmental Protection Agency under Section 404(b) of the Clean Water Act (33 U.S.C. § 1344(b)). An evaluation pursuant to the Guidelines indicates the project is not dependent on location in or proximity to waters of the United States to achieve the basic project purpose. This conclusion raises the (rebuttable) presumption of the availability of a less environmentally damaging practicable alternative to the project that does not require the discharge of dredged or fill material into special aquatic sites. The applicant has been informed to submit an analysis of project alternatives to be reviewed for compliance with the Guidelines.

PUBLIC INTEREST EVALUTION: The decision on whether to issue a Department of the Army Permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the project and its intended use on the public interest. Evaluation of the probable impacts requires a careful weighing of the public interest factors relevant in each particular case. The benefits that may accrue from the project must be balanced against any reasonably foreseeable detriments of project implementation. The decision on permit issuance will, therefore, reflect the national concern for both protection and utilization of important resources. Public interest factors which may be relevant to the decision process include conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people.

CONSIDERATION OF COMMENTS: USACE is soliciting comments from the public; Federal, State, and local agencies and officials; Native American Nations or other tribal governments; and other interested parties in order to consider and evaluate the impacts of the project. All comments received by USACE will be considered in the decision on whether to issue, modify, condition, or deny a Department of the Army Permit for the project. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, and other environmental or public interest factors addressed in a final environmental assessment or environmental impact statement. Comments are also used to determine the need for a public hearing and to determine the overall public interest in the project.

SUBMITTING COMMENTS: During the specified comment period, interested parties may submit written comments to Keith Hess, San Francisco District, Regulatory Division, Eureka Field Office, 601 Startare Drive, Box 14, Eureka, California 95501; comment letters should cite the project name, applicant name, and public notice number to facilitate review by the Regulatory Permit Manager. Comments may include a request for a public hearing on the project prior to a determination on the Department of the Army permit application; such requests shall state, with particularity, the reasons for holding a public hearing. All substantive comments will be forwarded to the applicant for resolution or rebuttal. Additional project information or details on any subsequent project modifications of a minor nature may be obtained from the applicant and/or agent or by contacting the Regulatory Permit Manager by telephone or e-mail (cited in the public notice letterhead). An electronic version of this public notice may be viewed under the Public Notices tab on the USACE website:   https://www.spn.usace.army.mil/Missions/Regulatory.


Regulatory Links

Redirecting...

Contact Information

Department of the Army
San Francisco District, Corps of Engineers
Regulatory Division
450 Golden Gate Ave., 4th Floor
San Francisco, California 94102-3404

Phone Number: (415) 503-6795
Fax Number: (415) 503-6693
cespn-regulatory-info@usace.army.mil